Block A-1 Alley Construction – Downtown Westminster

The City is embarking on construction of the Block A-1 alley project in Downtown Westminster. This project will construct a new public alley linking Harlan Street to Westminster Blvd. When completed, the alley will provide public access and utility links to future development within Block A-1 of the Downtown. For now, the alley will enhance access to the public parking lot located west of the Ascent and south of the Origin Hotel.

The Alley will be completely closed until June 1, 2024. In the meantime, a temporary entrance to the parking lot will be constructed off Westminster Boulevard and detour routes will lead patrons to the new temporary entrance.

 

Project Timeline

September 21, 2023

 

October thru November 2023

Closing of alley and construction of temporary entrance. Detours installed for vehicles and pedestrians.

 

Begin demolition.

October thru November 2023

Installation of utilities.

December – April 2024

Install curbs, gutters, and retaining walls.

May 2024 

Asphalt paving and completion.