Homepage > News

News

Wednesday, April 6, 2022

Sheridan Traffic Pattern Changes Start Next Week for Underpass Construction

Traffic pattern changes on southbound Sheridan Boulevard start overnight Wednesday, April 13th.

Sheridan Boulevard between Turnpike Drive and the eastbound U.S. Highway 36 ramps will be in a temporary lane configuration through summer 2022. The southbound lanes of Sheridan Boulevard will shift east in order to construct the western half of the new underpass serving the US 36 Bikeway users.

Drivers should expect overnight lane closures and traffic shifts on Wed., April 13 from 8 p.m. to 5 a.m. on Thursday morning while the contractor restripes southbound Sheridan Boulevard and prepares the road for the new configuration.

Two lanes will remain open in each direction on Sheridan Boulevard during the phased underpass construction. View the construction phasing map.

 

Project Background:
The Sheridan Boulevard Multimodal Transportation Improvement project – known as the Sheridan Underpass – is a federal transportation investment in mobility for all modes of travel. This project creates a direct bicycle and pedestrian connection between Downtown Westminster and the Regional Transportation District’s US 36 and Sheridan Station. Several improvements to Sheridan Boulevard are also part of the project.

 

Project Highlights: The contractor team led by CEI will construct major roadway improvements on Sheridan Boulevard through early 2023. Project features include:

  • Widening Sheridan Boulevard to six lanes from Turnpike Drive to West 88th Place
  • Constructing a new US 36 Bikeway underpass connecting Downtown Westminster to the RTD US 36 and Sheridan Station
  • Upgrading traffic signals at the Sheridan Boulevard / West 88th Avenue intersection
  • Placing curb ramps, concrete medians, streetlights and pedestrian lights
  • Improving storm sewer drainage system

 

Travel Impacts:
Construction activities will be phased to minimize traffic impacts. Two lanes will remain open in each direction on Sheridan Boulevard during construction, and access to adjacent properties will be maintained.

The US 36 Bikeway is closed between West 88th Avenue and West 92nd Avenue to accommodate construction. Local bike and pedestrian detours are in place.

All work is weather-dependent, and the schedule is subject to change.

 

For more information and project updates:

Call:             303-219-9033

Email:           sheridan-underpass@workzone.info

Visit:             www.westminsterco.gov/SheridanUnderpass

Text:             SHERIDAN to 21000 to sign up for travel alerts

Number of views (25479)/Comments (0)

Recent News

1345678910Last
All Articles

Newsletter Sign-up